Scheduled
The jail: approved in 2019, with substantial completion expected in the second quarter of 2031.
Arrival
I came to Mott Haven because a jail is being built here. What held my attention was what happens around the construction site: noise from work the City authorized to start at six in the morning; dust, which the site’s own monitors measure; and vibration, which people described to me and which is the one you cannot close a window against. I wanted to know what authorizes them.
Where the study area falls
The study area, and the parcels the records this project follows have touched, are set out on TRANSFERRED, where the map of them is.
The jail’s own schedule
The City’s own documents give the jail one completion date. The Department of Design and Construction’s community advisory of December 2025 gives the second quarter of 2031; its Community Design Workshop form gives the same quarter as substantial completion; its Community Board 1 presentation of March 2026 gives the summer of 2031; the kick-off for Phase 1 gives the first quarter of 2026 to the second quarter of 2031; and the Independent Rikers Commission’s Blueprint of March 2025 gives 2031 for the Bronx, 2029 for Brooklyn and 2032 for Queens and Manhattan. The foundation work runs from July 13, 2026 to February 2027.1
The jail in Mott Haven is one of four facilities intended to replace the jails on Rikers Island,2 approved by the City Planning Commission in September 2019, following a commission’s recommendation to close the Rikers complex. The City’s jails have been under federal court supervision since 2015. The court’s monitor measures the average monthly rate of use of force per 100 people in custody from 2016, which he calls “the time the Consent Judgment went into effect”: 3.96 that year, 12.23 in 2021, and 8.48 in the first half of 2025. In the monitor’s words, “use of force rates have not improved since the Consent Judgment went into effect.”3
Of everything on this ground, the jail carries the most dates. It has an application number, a commission report, an environmental review, a special permit, a construction program4 and a closure date it is pegged to. Almost nothing else here has a date at all, and the jail’s dates make that visible.
The City says why it is building them. Its Office of Criminal Justice states that “under Mayor Zohran Mamdani’s administration, Closing Rikers is the cornerstone of a safer, fairer, and more dignified city”, and that “a better future begins with four Borough-Based Jails”. The law says when it is to happen, and what form it takes: by 31 August 2027 the whole of Rikers Island is to pass to the City’s Department of Citywide Administrative Services, and the Department of Correction may no longer use it to house incarcerated people. The building agency says when the building ends. Its own community advisory for this site closes sidewalks and parking along the Southern and Bruckner frontages “Beginning on Monday 12/29/25 through Q2 2031”, and the Phase 1 kick-off gives its construction schedule as the first quarter of 2026 to the second quarter of 2031.5 The date the jail is to be finished is nearly four years after the date by which the law requires the Department of Correction to stop housing people there.6
The program that builds them describes the facilities as more than jails: as buildings with community space, with retail at the base, with services, placed near courts and near the families of the people held in them.
That description is not only rhetoric, and it is not decoration. It is written into the instruments. This site’s own special permit allows community facility and commercial use at the base of the building.7 A jail authorized by an instrument that also determines what the street sees at eye level is a jail that, in the permission itself, reads from the sidewalk as something other than a jail. There is a term for this in the literature: James Kilgore’s carceral humanism, the delivery of carceral capacity in the vocabulary of care, services and repair.8
The same logic reaches the counting. The most recent plan for the system that replaces Rikers adds secure treatment beds in city hospitals to the beds in the four borough jails, and reports them in a single total. Capacity that is not in a jail is counted with capacity that is.9
The mechanism by which Rikers is to be closed is not a decision about prisons. It is a decision about land. The City’s own environmental review describes it as a separate land use action prohibiting detention on the island, and the commission’s report of the same month describes the step as commencing a zoning process to demap it.10
This is the same class of instrument that produced the site in Mott Haven. A map change rezoned a hundred-foot strip of Concord Avenue. A zoning text amendment created a special permit that exists for this program and no other. The closing date was first written in October 2019, in an application to change the City Map, filed by the Department of Correction, the Mayor’s Office of Criminal Justice and the Council Speaker two days before the Council approved the four jails: no incarceration on Rikers after December 31, 2026. In October 2020, two days before the City Planning Commission voted, the applicants revised the date to August 31, 2027, citing “delays in procurement and design due to the COVID-19 pandemic.” Local Law 16 of 2021 set the same date for transferring the island out of the Department of Correction.11 The closing of one jail system and the siting of its replacement are not two policies that happen to coincide. They are the same administrative object, pointed in two directions.
And that tells you what the closure is and is not. A map change persists until another map change amends it; it is durable in exactly the way the permits above are not. But it prohibits a use. It does not oblige anyone to finish a building. A demapping can be entirely in force while nothing is built anywhere, and the record would show the city in compliance with the instrument and nowhere near the outcome the instrument was passed to produce.
Both dates come from one application to change the City Map: December 31, 2026 as filed, August 31, 2027 as revised. Local Law 16 of 2021 carries the later date, by which the island is to pass to another agency and the Department of Correction is to stop housing incarcerated people there.12
What authorizes it
Each of the three is governed, and each is governed differently — and the differences are not about how much harm any of them does.
Noise is governed by a permission with a term. Work outside permitted hours requires an authorization from the Department of Buildings, and each one runs for a short fixed period before it has to be applied for again.13 The hours these authorizations cover, and the hours noise and vibration are monitored, are set out in MONITORED HOURS.
Vibration is governed by a requirement rather than a permission. The building code obliges an excavation to monitor the buildings within a set distance of it, under a plan the Department of Buildings finds acceptable. The monitoring happened, and the monthly reports record it. The plan itself is not public.14
Dust is governed by neither. The citywide rules are practices — wetting, covering, containing — with nothing to apply for, no term and no renewal. The only dated instrument attaching to this site is a plan for handling contaminated ground, approved in March 2019, which applies while the ground is open and ends with a closure report before occupancy.15
So the administrative attention a nuisance receives here is not a measure of what it does to anyone. It is a measure of what the apparatus can make of it. Noise can be made into a permission, so it acquires dates, terms and renewals. Vibration can be made into a requirement, so it acquires a plan that someone must approve. Dust can be made into neither, so it has practices.
And a permission with a term is a strange object. It expires, and it can be applied for again, so a thing that is temporary in form can be continuous in fact. I had come to look at noise and found a question about duration.
The same instruments, issued by the same agencies and recorded in the same registers, decide whether a building is repaired, who is registered as its owner, and what may be built on the lot next door.
The City Planning Commission’s report describes the Bronx site as “not contiguous to the Bronx Hall of Justice.” The jail lot is 1.45 miles from the Hall of Justice, measured parcel center to parcel center. Every court appearance will mean a journey between the two.16
Objection
Bronx Community Board 1 recommended disapproval of the site selection, and of the special permit and the zoning map change, in 2019. The site selection proceeded.17
Diego Beekman Mutual Housing Association HDFC and Walter Nash brought an Article 78 proceeding against the City and its agencies over the siting. The petition was dismissed in March 2021, and the appeal was deemed withdrawn by the Appellate Division in April 2022.18
The routes available for objecting were procedural routes, and procedural routes test procedure. Where the procedure was followed, the challenge failed.
Jack Norton, Lydia Pelot-Hobbs and Judah Schept write:19
“Anti-jail organizers must be adept at maneuvering the often mundane politics of land-use policy, from canvassing against new jail taxes to learning the county planning procedures to conducting political education about the false promises of jails as economic development or sites of care. … The long-haul work of jail struggles pushes us to contest not only the physical jail but the carceral logics and practices that devalue the dignity and worth of certain people and places.”
“There’s this expression — plan or be planned for. I think that is one of the ultimate onuses our communities have to understand. Of all 59 community districts in New York City we rank at the bottom for voter turnout. There are a lot of factors behind that. What we know is that a lot of people are disillusioned by electoral politics. What we also know is that a lot of people are in survival mode. We are situated — not spiritually, not soulfully, but economically — in the poorest congressional district in the country.”
“Civil service jobs are breathtakingly common here in the Bronx. If you’re trying to stay here, you don’t have many other options than a service job, nonprofit work, or to go work for a public agency… jobs like working for the DMV, working for HRA, working for the Department of Corrections. These are all ways to find mobility where it may not otherwise exist.”
The agencies that administer these instruments are also, in this borough, among the ways a person stays in it. This is the condition the argument has to hold: the same public apparatus is the employer of last resort and the author of the orders.
Sources
Cited throughout
- City Planning Commission
- Department of Correction
- Department of Design and Construction
- Independent Rikers Commission
See THE GAP.